Methodology
With Brock's proven changeover strategy ensures that the customer’s existing system is not compromised or interfered with during the upgrade process.
Brock Technical Milestones
Find out what sets Brock Solutions apart from other professional services companies.
Zero Downtime
Brock's engineering specialists have developed a unique methodology and execution program to minimize changeover disruptions with Zero Downtime.
Packaged Control Rooms
Brock Solutions can custom-build Electrical Control Rooms (ECR) in our own facilities that meet any specification and then ship the completed control room to the customer's site.
Automated Press Line Upgrades

Brock Solutions supplies press line solutions to End Users, Service Centers, and OEMs with interests in the Automotive, Applicance and steel sectors. Our solutions focus increased product tolerances and throughput.

The Challenge: Brock Solutions was contracted by a leading North American automotive manufacturer to design, develop, supply and implement new control systems for three Footprint Press Lines in one of their stamping facilities. The impetus behind the project was the customer’s need to support the impending launch of new vehicle designs as well as to accommodate ongoing customer demands.

The Methodology: As the first phase of the project, Brock provided a detailed Functional Specification to outline both the hardware and software features as well as functionality proposed for the design. Brock’s Offsite Acceptance Test (OAT) using an I/O simulated environment ensured the software was fully written and tested before site trials. In addition, the OAT allowed the operators to experience a preview of the design and its expected functionality.

The Scope of Work: Brock Solutions was responsible for the automation of the Presses, which included:

  • Functional/Detail Design Specifications
  • Controls PLC hardware and software
  • Operator interface design and associated hardware and software
  • I/O Simulation
  • OAT
  • Start Up
  • Commissioning
  • IAT at mechanical rebuild facility
  • FAT on site

The Benefits: At this stage in the project, the first Press (out of fifteen in total) has been successfully commissioned and the following benefits acheived:

  • Improved reliability of equipment and production through-put capability
  • Enhanced safety features
  • Improved product quality